- RADA received only 59% of its J$3.1 billion funding requests.
- 67% of contracts awarded through limited tender, bypassing competition.
- Six contracts worth J$129.8 million violated open bidding rules.
- Four contractors captured 36% of all contract value awarded.
- 53 instances of critical drainage work omitted or reduced.
- Some rehabilitated roads deteriorated within just three to four months.
Read the full audit report from the Auditor General’s Department →
Jamaica’s farm road network — the arteries that carry food from field to market and sustain the livelihoods of thousands of rural families — has been the subject of a damning performance audit revealing that nearly J$2 billion in public funds produced roads that sometimes lasted no more than three months. The Auditor General’s review of the Rural Agricultural Development Authority’s farm road rehabilitation programme found serious failures in procurement, road selection, quality oversight, and contract management that together raised profound questions about whether taxpayers received any lasting value for their money. For Jamaican farmers, rural communities, and anyone who depends on agricultural supply chains, the findings carry consequences that reach far beyond the roads themselves.
When the Rural Agricultural Development Authority spent nearly two billion dollars rehabilitating Jamaica’s farm roads between 2015 and 2019, rural communities across the island were promised better access to markets, reduced post-harvest losses, and improved livelihoods for farming families. What the Auditor General of Jamaica found instead was a programme riddled with procurement irregularities, absent quality controls, a near-total lack of road inventory management, and physical works that in some cases deteriorated to their pre-repair condition within three to four months of completion.
The performance audit, covering the period 2014-15 to 2018-19, examined how RADA — the agency under the Ministry of Agriculture tasked with driving agricultural development — planned, procured, and executed farm road rehabilitation across Jamaica’s fourteen parishes. The findings, released in October 2019, painted a picture of an agency that lacked the systems, staffing, and strategic discipline needed to manage a programme of this scale responsibly.
RADA requested J$3.1 billion from the public purse over the audit period to rehabilitate farm roads. It received J$1.98 billion — roughly 59 cents of every dollar sought. That gap, while significant, cannot alone explain what went wrong. The audit found that RADA’s annual budget requests were not consistently grounded in its own Strategic Business Plans. In the 2015-16 financial year, for example, RADA’s strategic plan projected J$75 million in farm road expenditure, yet the agency submitted a budget request of J$500 million to the Ministry of Finance — a discrepancy of more than J$425 million that was never adequately explained to auditors. This misalignment between planning documents and budget submissions is not merely an administrative quirk; it signals that financial decisions were being made outside the discipline of strategic planning, with no clear accountability trail.
Compounding the budget irregularities was a structural failure in how RADA allocated the funds it did receive. Not a single dollar of the farm road budget was set aside for routine or preventative maintenance. Every allocation went toward rehabilitation — fixing roads that had already failed — rather than preserving those in reasonable condition. This approach guaranteed a cycle of deterioration and emergency spending, with farmers and rural communities bearing the cost of roads that would inevitably fail again.
The procurement record is where the audit’s findings grow most serious. Auditors reviewed 112 contracts collectively valued at J$1.6 billion. Of these, 75 contracts worth J$1.04 billion — 67 percent of the total by number — were awarded through limited tender, a procurement method that restricts competition to a small pool of pre-selected bidders. A further 33 contracts, valued at J$520.93 million, were processed as direct or emergency procurement. Only four contracts, worth J$90.8 million, went through local competitive bidding — the open, transparent process that government procurement rules are designed to mandate for contracts above certain thresholds.
The rules in question are unambiguous. Government guidelines required open competitive bidding for contracts exceeding J$20 million. Six of the limited tender contracts reviewed by auditors breached that threshold, collectively valued at J$129.8 million. These were not borderline cases; they represented clear non-compliance with procurement regulations that exist specifically to protect the public interest, prevent the concentration of government work among favoured contractors, and deliver value for money on public spending.
The concentration concern is borne out directly by the numbers. Four contractors between them were awarded 42 contracts worth J$613.9 million — 36 percent of the entire J$1.6 billion contract pool reviewed. That level of concentration in a public works programme of this nature raises obvious questions about whether competition was genuinely open and whether the public was receiving the best possible value. RADA’s due diligence on contractors was limited to verifying tax compliance certificates and National Contracts Commission registration. No prequalification assessments were conducted. There was no evaluation of contractors’ technical capacity, equipment holdings, financial stability, or track record of delivering quality work — precisely the kind of vetting that might have prevented some of the quality failures that followed.
Those failures were widespread. Auditors documented 53 separate instances where drainage works that had been identified as critical components of road rehabilitation were either omitted entirely or scaled back during execution. Drainage is not peripheral to road construction in Jamaica’s climate; it is foundational. Without proper drainage, road surfaces absorb water, soften, and break apart. In a country that experiences heavy tropical rainfall and is increasingly exposed to intense weather events driven by climate change, omitting drainage work is not a cost-saving measure — it is a guarantee of accelerated failure.
Nine roads were replaced through variation orders — formal contract amendments — at a total additional cost of J$50.7 million. Variation orders are a legitimate tool in construction management, used to accommodate unforeseen site conditions. But when roads are being substituted wholesale, rather than individual scope items being adjusted, it suggests that original road selections were inadequately assessed, that planning was deficient, or that the variation order mechanism was being used to direct work to different locations outside the original competitive process. Auditors found the controls around variation orders to be inadequate.
An internal audit referenced in the Auditor General’s findings was particularly stark: some roads that had been rehabilitated under the programme deteriorated back to poor condition within just three to four months of completion. The public cost of this is not simply the wasted expenditure on those specific roads — though that is real and significant — it is also the compounded economic harm suffered by the farmers and rural communities who depended on those roads being passable. Delayed harvests, spoiled produce, inaccessible markets, and higher transportation costs translate directly into lost income for farming families operating on thin margins.
A survey conducted as part of the audit examined three rehabilitated roads and found that 71 percent of farmers reported improved farm access following rehabilitation. That figure sounds encouraging until set beside the finding that 34 percent of those same farmers reported persistent poor drainage problems — problems that, if the pattern identified elsewhere in the audit holds, will translate into premature road deterioration and a return to impassable conditions within months or years.
Underpinning these quality failures was a capacity problem of striking severity. Only four works engineers were assigned responsibility for quality oversight of farm road rehabilitation across the entire island of Jamaica. Four engineers — covering fourteen parishes, hundreds of roads, and J$1.6 billion in contract work. The inspection checklists those engineers were expected to use lacked documentation of testing frequency and results, meaning that even the limited oversight capacity that existed was not being systematically deployed or recorded.
The road inventory failures add another layer of dysfunction. RADA could not distinguish, within its own data systems, between farm roads under its mandate and parochial roads that fall under the responsibility of municipal corporations. This basic information gap meant that RADA’s priority lists for rehabilitation were drawn up without a reliable foundation. The audit found that some roads selected for rehabilitation from parish office priority lists were not farm roads at all. The St. Mary parish office road, for example, received J$5.6 million in rehabilitation works that should not have been charged to the farm road programme. RADA had identified only 408 roads covering approximately 960 kilometres of its estimated 1,500-kilometre network, and maintained no master road inventory system. Without knowing what roads exist, where they are, and what condition they are in, rational resource allocation is impossible.
RADA accepted most of the Auditor General’s recommendations, which included aligning strategic plans to budget realities, implementing a GPS-based road inventory system, strengthening quality assurance procedures, establishing a contractor performance register, and coordinating with the Planning Institute of Jamaica and the Statistical Institute of Jamaica to measure the economic impact of farm road improvements. These are sensible, proportionate recommendations. The problem — and it is a recurring problem identified in accountability audits across Jamaica’s public sector — is that RADA provided no specific timelines for implementing the majority of its accepted commitments, and no clear resource allocation to support them. Committing to include farm road maintenance as a budget line item and indicating an intent to develop a GPS inventory system are steps in the right direction, but intent without a delivery schedule and assigned responsibility is not accountability.
What the RADA farm road audit ultimately reveals is a systemic failure that extends beyond any individual contract or any single parish. A development agency with a mandate to support Jamaica’s agricultural sector and rural communities spent five years and nearly two billion dollars on a programme that was under-resourced relative to need, improperly procured in the majority of its contract value, inadequately supervised on the ground, and insufficiently tied to any system capable of measuring whether the investments were working. The four engineers tasked with island-wide oversight, the absent drainage works, the roads that crumbled within a season — these are not isolated incidents. They are symptoms of an agency operating without the governance infrastructure that a programme of this scale demands.
For Jamaica’s agricultural sector to fulfil its potential under Vision 2030, farm road infrastructure must be treated as a strategic asset requiring sustained, disciplined investment — not as an annual rehabilitation exercise conducted outside competitive procurement rules and managed by a workforce too small to do the job properly. The Auditor General’s findings are a detailed record of what happens when public programmes are funded without the institutional capacity to execute them well. Whether RADA and the Ministry of Agriculture take those findings as the basis for genuine structural reform, or respond with accepted recommendations that quietly disappear into filing cabinets, will determine whether the next five years of farm road spending produces lasting results or simply repeats the same cycle of expenditure, deterioration, and failure.
Jamaica Accountability Watch is an independent editorial series by Jamaica Homes News examining what government audit reports reveal about the management of public money. Source: Auditor General’s Department of Jamaica.
Follow Jamaica Homes on Youtube @jamaicahomes and Instagram @jamaica_homes and on Facebook @jamaicahomes Send us a message or email us at onlinefeedback@jamaica-homes.com or editor@jamaica-homes.com
Support independent Jamaican journalism.
- 1Our journalists cover housing, politics and community — stories that directly affect Jamaican lives.
- 2We have no billionaire owner and no advertisers calling the shots. Every story is decided by our editors.
- 3It costs less than a cup of coffee a week, and takes less time to subscribe than it took to read this article.
Support Jamaica Homes News today.
- Save 17% compared to monthly
- All articles unlocked
- Weekly newsletter
- Priority support
By subscribing you agree to our Privacy Policy and Terms.
