Update, 7 November 2026: opening target moves to winter season
MONTEGO BAY, Jamaica — The September completion target reported below was not met. In an interview published by The Gleaner on 6 November, Works Minister Robert Morgan said the National Road Operating and Constructing Company (NROCC) and its contractor were working towards opening the Montego Bay Bypass before the 2026–27 winter tourist season. This is a revised expectation, not a confirmed opening date.

Morgan cited inclement weather and construction challenges as factors affecting progress. His comments follow his September 9 site visit, when the bypass was described as roughly 90 per cent complete and expected to be ready that month. The November report makes clear that the original deadline slipped. No new independently verified completion percentage was supplied in that account.
For residents, businesses and prospective property buyers, the delay matters because the route is intended to ease congestion through Montego Bay and improve connections between communities, commercial areas and Sangster International Airport. Until the bypass actually opens, journey-time benefits remain prospective. Buyers and landlords should not treat projected travel savings as established facts when assessing a property’s accessibility or rental appeal.
The minister said NROCC’s project team was pressing towards the revised opening window, but weather and remaining works could still affect delivery. The original article below records the position as reported on 13 September; it is retained for transparency rather than silently rewritten. Source: The Gleaner, 6 November 2026.
Montego Bay, St James, 13 September 2026
The Montego Bay Bypass is about nine-tenths finished and is expected to be completed before the end of this month, the Government says, bringing western Jamaica closer to relief from the traffic that regularly chokes Jamaica’s second city.
Robert Morgan, the minister with responsibility for works, gave the update after touring the road on Wednesday, 9 September, with representatives of the National Works Agency, the National Road Operating and Constructing Company, contractor China Harbour Engineering Company and other stakeholders.
Finishing touches
The project is now in its final phase. New road signs are up along the corridor, guardrails are in place and the central barrier separating traffic flowing in opposite directions is largely done. Mr Morgan described the first phase of the Montego Bay Perimeter Road as among the most significant infrastructure works the country has undertaken.
The bypass is one piece of that wider perimeter road scheme, which stands at roughly 87 per cent complete overall. Other elements include the Long Hill Bypass and road upgrades running to Barnett Street and West Green.
Who benefits
Motorists in St James and Hanover are expected to see the biggest improvement, with drivers from Westmoreland and Trelawny also set to gain. The new route should make it easier to reach Sangster International Airport and the parish’s main business districts.
One question remains open: whether drivers will pay to use it. Mr Morgan said no decision on tolling had been taken and that several options were still being weighed, to be settled in discussion with the Prime Minister, who holds the works portfolio.
Part of a wider road programme
The minister placed the bypass alongside other national projects, including the South Coast Highway Improvement Project from Harbour View to Portland, the Port Antonio Bypass and the finished Williamsfield leg of Highway 2000. He also pointed to plans for a road linking Mammee Bay in St Ann to Trelawny and for widening the North Coast Highway west towards St James. During the same visit, the team inspected SPARK road improvements in the Flanker and Norwood areas.
For homeowners and buyers in western Jamaica, shorter and more predictable journeys can widen the range of communities that are practical to live in while working in Montego Bay. Anyone weighing a purchase or rental near the corridor will also want to watch the tolling decision, since it could affect day-to-day travel costs.