The bidding round for 300 megawatts of renewable power and 150 megawatts of battery storage, billed as the largest renewable energy tender in the Caribbean, has been pushed back to the final quarter of 2026, delaying a key step towards Jamaica’s 2030 clean energy goal.

KINGSTON, Jamaica, 8 October 2026, Jamaica’s largest planned renewable energy tender will now open before the end of the year rather than in the summer, after the agency responsible for buying new power generation said it needs more time to finalise the bidding documents.
The Generation Procurement Entity (GPE) said in an October market update that it now expects to publish the request for proposals in the fourth quarter of 2026, the Gleaner reported. The tender will seek up to 300 megawatts of renewable generation and 150 megawatts of battery storage.
What has changed
The scale of the tender is not new. The Minister of Energy, Transport and Telecommunications announced the 300 megawatt and 150 megawatt targets in the Sectoral Debate in May, according to the Jamaica Information Service, which reported at the time that the tender was scheduled to be completed by August 2026. The GPE had earlier sought information in March on a smaller round of 220 megawatts of generation and 110 megawatts of storage, so the May announcement enlarged the programme by more than a third.
What is new is the timetable. The GPE had previously expected the auction to launch in the third quarter, which ended in September. It now says the extra time will allow it to complete procurement documents, take on board feedback from developers, lenders, technology suppliers and industry groups consulted in June, finalise technical and commercial terms and complete governance and approval steps, and it also pointed to policy considerations and evolving market conditions. Following the consultations, it has refined the draft power purchase agreement, technical specifications and evaluation method. The storage element will be open to any commercially proven technology that meets the technical requirements.
The road to 2030
The tender is central to Jamaica’s goal of producing half its electricity from renewable sources by 2030. The Jamaica Information Service reported in May that renewables supplied about 15 per cent of the country’s electricity, and that current and planned projects were expected to add roughly 35 percentage points. The GPE awarded about 100 megawatts of solar contracts in November 2024.
The Gleaner noted that adding the new 300 megawatts to existing capacity would take installed renewables to nearly 590 megawatts, more than half of a grid of roughly 1.02 gigawatts. It also cautioned that installed capacity is not the same as the share of electricity actually produced, since solar and wind generate only when the sun shines and the wind blows. That is precisely why the battery component matters: storage allows solar output captured during the day to be used after sunset.
Why households should care
Electricity is a recurring cost for every household, landlord, tenant and business, so the make-up of the generation mix matters well beyond the energy sector. With renewables supplying only about 15 per cent of power, most of Jamaica’s electricity still comes from conventional generation, and the Minister framed the new programme in May as a way of strengthening energy security and reducing exposure to global oil price volatility. Large scale renewables with storage, bought through competitive bidding, offer the prospect of more stable generation costs over the life of long term contracts, though any effect on tariffs depends on the prices bid, the regulator and the time it takes to build the plants.
A delay of a few months is not unusual for a procurement of this size, and getting the contract terms right may matter more than the launch date. But each slip pushes back the point at which new plants connect to the grid, and the 2030 deadline is now little more than four years off. Projects still have to be bid, awarded, financed, built and connected in that window.
Land, rooftops and resilience
The tender also has a land dimension. Utility scale solar farms need large, accessible sites close to transmission lines, so site selection, leases and land acquisition will be part of how quickly winning projects can move from contract to construction.
Alongside the utility tender, the Minister said in May that the Government plans a further 100 megawatts of distributed renewables through a strengthened net billing programme for homes and businesses, with an online application platform expected by December 2026. For homeowners weighing rooftop solar and batteries, that programme may prove the more immediate change.
The direction of travel is clear and broadly shared: more renewable power, more storage and less exposure to volatile fuel prices. The GPE’s revised schedule now puts the onus on the final quarter of the year. Whether the request for proposals appears before December, and whether it draws strong bids, will be an early indicator of how realistic the 2030 target remains, and of how soon Jamaican households might see the benefit on their bills.
Follow Jamaica Homes on Youtube @jamaicahomes and Instagram @jamaica_homes and on Facebook @jamaicahomesnews Send us a message or email us at onlinefeedback@jamaica-homes.com or editor@jamaica-homes.com


Visit our YouTube Community ↗