- J$100 million water system commissioned
- About 3,000 Trelawny residents to benefit
- Belfield well and pumping equipment upgraded
- Road repairs remain an outstanding concern
KINGSTON, Jamaica, 12 October 2026
A J$100 million upgrade to the Bounty Hall water supply system and Belfield well has been commissioned in Trelawny, bringing improved service prospects to approximately 3,000 residents who have endured recurring shortages. The National Water Commission (NWC) investment was officially commissioned on 8 October and reported by the Jamaica Information Service on 12 October.
The work is relevant to homes across Bounty Hall and neighbouring communities, where unreliable piped water has forced households to depend on storage and alternative supplies. The commissioning marks the completion of substantial infrastructure works, but the longer-term test will be whether pressure and availability remain dependable during dry periods and equipment failures.

What has changed in the network
The Belfield rehabilitation included a replacement pump and motor, electrical and mechanical improvements, chlorination equipment and associated pipework. Approximately 300 metres of 12-inch ductile iron main were installed. At Bounty Hall, the NWC upgraded the power and pumping arrangements, adding duty and standby pumps and related connections.
The communities identified as served include Bounty Hall, New Garden, Hampden Land, Cargen, Green Park and Hermitage. The work is intended to make the distribution system more reliable, rather than simply provide a temporary response to an individual breakdown.
Why residents will be watching closely
Water reliability has been a persistent problem in this part of Trelawny. In March 2026, residents of Bounty Hall had only just regained regular supplies after weeks of disruption linked to faults at the Martha Brae Water Treatment Plant. At that time, the NWC also reported that the Belfield well had returned to operation to increase flows to the Bounty Hall reservoir.
The latest investment therefore needs to be judged against a documented history of interruptions, not just the fact that new equipment has been switched on. For householders, a functioning connection affects sanitation, everyday costs and the practicality of occupying or improving a property. Prospective buyers should still check whether a particular house has an active NWC connection, adequate pressure and sufficient storage.
Municipal representatives have also raised a separate issue: sections of roadway damaged during pipe installation still require attention. The water improvements are a significant gain, but unfinished road reinstatement can leave residents with another infrastructure problem after construction crews depart.
The NWC is expected to assist residents with customer registration and connections. A system serving a community does not automatically mean every individual property is connected, and residents should confirm their own arrangements directly with the utility.
Follow Jamaica Homes on Youtube @jamaicahomes and Instagram @jamaica_homes and on Facebook @jamaicahomesnews Send us a message or email us at onlinefeedback@jamaica-homes.com or editor@jamaica-homes.com